We moved from southeast London to Norwich in late 2012 with the dream of building a home for our family that would require as little energy as possible to run and that would use materials with the minimum possible impact on the environment. Late May 2013 and the journey really began as we started the search for a plot to build on.

Saturday 31 January 2015

Find us on Facebook

Apologies for the lack of posting on this "Blogspot" blog. We've found that a Facebook Page is far easier to manage on the go (we're on the go a lot now that we're working on site) and works much better with our images. Time is precious so we can't keep 2 blogs going.

From now on, you can keep up with the project at. . .
www.facebook.com/zerocarbonbods

























A quick summary of what we've been up to since Christmas.

w/c 5th Jan - Setting out.

  • Site clearance
  • Corner pegs
  • profile boards
  • datum points and levels
w/c 12th Jan - Groundworks.
  • Site entrance and temp hardcore drive
  • Site strip and muck-away
  • Foundation trenches
  • Foundation concrete (C30) pour
  • Start foundation blocks
  • Oversite strip down to drains level
w/c 19th Jan - Groundworks.
  • Drains setting out
  • Continue foundation blocks
  • Foamglas Perinsul H blocks
  • Start 150mm oversite hardcore backfill
  • Services ducting
  • 40mm Binding sand layer over hardcore

w/c 26th Jan - Groundworks / Scaffolding

  • Complete all foundation block work
  • Complete oversite backfill - 150mm hardcore & 40mm blinding sand
  • DPM (1200g)
  • 200mm Celotex sub-slab insulation
  • 500g separating layer
  • Gen3 fibre reinforced (Fibremesh 150) concrete oversite floor slab pour.
  • Install 2 lift scaffold with gable hop-ups around perimeter of oversite.
and still to come. . . . . . . 

w/c 2nd Feb - Timber frame
  • Sole plates
  • Ground floor internal and external panels
w/c 9th Feb - Timber frame
  • Ground floor internal and external panels
  • Ground floor head plates and rim boards
  • First floor deck - joists and floor panels
  • 2nd floor internal and external panels
w/c 16th Feb - Timber frame
  • 2nd floor internal and external panels
  • 2nd floor head plates and rim boards
etc. . . . .