From now on, you can keep up with the project at. . .
www.facebook.com/zerocarbonbods
A quick summary of what we've been up to since Christmas.
w/c 5th Jan - Setting out.
- Site clearance
- Corner pegs
- profile boards
- datum points and levels
w/c 12th Jan - Groundworks.
- Site entrance and temp hardcore drive
- Site strip and muck-away
- Foundation trenches
- Foundation concrete (C30) pour
- Start foundation blocks
- Oversite strip down to drains level
w/c 19th Jan - Groundworks.
- Drains setting out
- Continue foundation blocks
- Foamglas Perinsul H blocks
- Start 150mm oversite hardcore backfill
- Services ducting
- 40mm Binding sand layer over hardcore
w/c 26th Jan - Groundworks / Scaffolding
- Complete all foundation block work
- Complete oversite backfill - 150mm hardcore & 40mm blinding sand
- DPM (1200g)
- 200mm Celotex sub-slab insulation
- 500g separating layer
- Gen3 fibre reinforced (Fibremesh 150) concrete oversite floor slab pour.
- Install 2 lift scaffold with gable hop-ups around perimeter of oversite.
and still to come. . . . . . .
w/c 2nd Feb - Timber frame
- Sole plates
- Ground floor internal and external panels
w/c 9th Feb - Timber frame
- Ground floor internal and external panels
- Ground floor head plates and rim boards
- First floor deck - joists and floor panels
- 2nd floor internal and external panels
w/c 16th Feb - Timber frame
- 2nd floor internal and external panels
- 2nd floor head plates and rim boards
etc. . . . .